Update | Undersea tunnel of Shenzhen-Zhongshan Link completes docking

On June 11, the subsea tunnel of the Shenzhen-Zhongshan Link successfully joined with the eastern tunnel, linking together Shenzhen and Zhongshan under the Lingdingyang Sea.

[Photo provided to GDToday]

As a core project in the GBA, the Shenzhen-Zhongshan Link boasts a total length of 24 kilometres, 6.8 kilometres of which is the undersea tunnel.

[Photo provided to GDToday]

According to the engineers, they have taken advantage of the Beidou system and other techniques to ensure the precision of the docking.

[Photo provided to GDToday]

During the tunnel engineering, cutting-edge technologies were also used to limit the settlement of soft soil foundations to within 48 mm, setting a new world record.

[Photo provided to GDToday]

Up to now, a total of 35 million cubic meters of sediments have been dredged up as the first step of tube installation, which can fill 14,000 standard swimming pools.

[Photo provided to GDToday]

Around 320,000 tons of steel in total were used in the underwater tunnel, equaling three times the amount used in the “Bird’s Nest” Stadium. Also, nearly 90 cubic meters of self-compacting concrete were poured into the tube sections, with the density reaching the world-class level.

[Photo provided to GDToday]

The tunnel is expected to be finished in November 2023. Next, the artificial island project will be carried out as scheduled, with the engineering of several fields in full swing, as part of the efforts to open the Link to traffic in 2024.

Author | Fanny, Poster (intern)