Shenzhen-Zhongshan Cross-sea Link makes progress in immersed tunnel construction

2021-Sep-17       Source: Newsgd.com

On September 15, the E12 immersed tube of the Shenzhen-Zhongshan Cross-sea Link was embedded after 25 hours of undocking, transport, mooring, and installation. Now the total length of the installed im

On September 15, the E12 immersed tube of the Shenzhen-Zhongshan Cross-sea Link was embedded after 25 hours of undocking, transport, mooring, and installation. Now the total length of the installed immersed tube tunnel reached over 2000 meters, which is a big achievement for the Link's construction.

It is estimated that the whole tunnel, which is made up of 32 tubes, will be finished in 2023 under the Lingding Channel.

The 24-kilometer link connecting the cities of Shenzhen and Zhongshan will play an essential role in the development of the Guangdong-Hong Kong-Macao Greater Bay Area. The Shenzhen-Zhongshan Cross-sea Link will open to traffic in 2024. It will cut travel time between the two cities from two hours to 30 minutes.

On September 15, the E12 immersed tube of the Shenzhen-Zhongshan Cross-sea Link was embedded.(Photo Provided to Newsgd.com)

On September 15, the E12 immersed tube of the Shenzhen-Zhongshan Cross-sea Link was embedded.(Photo Provided to Newsgd.com)

On September 15, the E12 immersed tube of the Shenzhen-Zhongshan Cross-sea Link was embedded.(Photo Provided to Newsgd.com)

Reporter: Nan

Editor: Keane, Jerry

Editor: Will

Scan to share on WeChat

Scan to follow us on WeChat

Related News

Home|About us|Contact us|Southcn.com

WWW.NEWSGD.COM. All rights reserved.

WWW.NEWSGD.COM. All rights reserved.|Registered number 020074| 粤公网安备 44010402000511号|ICP备案号粤B-20050235